1-
|
Tests derived from behavioral class models should be based on the ?
|
|
A -
|
data flow diagram
|
|
B -
|
object-relation diagram
|
|
C -
|
state diagram
|
|
D -
|
use-case diagram
|
2-
|
Effective software project management focuses on four P's which are ?
|
|
A -
|
people, performance, payoff, product
|
|
B -
|
people, product, performance, process
|
|
C -
|
people, product, process, project
|
|
D -
|
people, process, payoff, product
|
3-
|
The first step in project planning is to ?
|
|
A -
|
determine the budget.
|
|
B -
|
select a team organizational model.
|
|
C -
|
determine the project constraints.
|
|
D -
|
establish the objectives and scope.
|
4-
|
Process framework activities are populated with ?
|
|
A -
|
milestones
|
|
B -
|
work products
|
|
C -
|
QA points
|
|
D -
|
All of the above
|
5-
|
Which of the following is not generally considered a player in the software process?
|
|
A -
|
customers
|
|
B -
|
sales people
|
|
C -
|
project managers
|
|
D -
|
end-users
|
6-
|
The best project team organizational model to use when tackling extremely complex problems is the ?
|
|
A -
|
closed paradigm
|
|
B -
|
open paradigm
|
|
C -
|
random paradigm
|
|
D -
|
synchronous paradigm
|
7-
|
Which factors should be considered in choosing the organizational structure for a software team? (Select all that apply) ?
|
|
A -
|
degree of communication desired
|
|
B -
|
predicted size of the resulting program
|
|
C -
|
rigidity of the delivery date
|
|
D -
|
All of above
|
8-
|
One of the best ways to avoid frustration during the software development process is to ?
|
|
A -
|
give team members more control over process and technical decisions.
|
|
B -
|
give team members less control over process and technical
|
|
C -
|
hide bad news from the project team members until things improve.
|
|
D -
|
reward programmers based on their productivity.
|
9-
|
Which of these software characteristics is not a factor contributing to project coordination difficulties?
|
|
A -
|
interoperability
|
|
B -
|
performance
|
|
C -
|
scale
|
|
D -
|
uncertainty
|
10-
|
Which of these software characteristics are used to determine the scope of a software project?
|
|
A -
|
context, lines of code, function
|
|
B -
|
context, function, communication requirements
|
|
C -
|
information objectives, function, performance
|
|
D -
|
communications requirements, performance, information objectives
|